If you are building or renovating your home, this page will provide you with information and the forms you need to complete.

Step one: Complete the Connection Application form  

  • You can request a supply upgrade using the Connection Application form.
  • Submit the completed form online, or to your local Horizon Power office.
  • Do you also require a CT meter? Complete the Request for a CT meter form below as well.
  • Connections are assessed and quoted on a case-by-case basis. However, you may be eligible for the subsidised rate for an underground point of supply. 

 

Step two: Pay the Design Fee

A design fee of $6,195.00 is payable for projects involving:

  • the supply of electricity to a connection with a total maximum load of between 31 kVA and 1000 kVA or 10% of the relevant systems peak load; or
  • CT metering that will result in an increase in the load capacity at the relevant site.

Step three: Accept the formal quote

Once you have received the formal quote and you want to proceed, simply sign the Quote Acceptance form and return it to us.

We will issue an invoice for the work which will need to be paid before any scheduling or construction can begin.

Please note: commencement of your works may take up to 12 weeks following the payment of your construction invoice.

Step four: Open an account with us and ask for a customer reference number

You can request a customer reference number (CRN) by phoning 1800 267 926 or you can complete a request to install a new temporary or permanent meter using the form below.

Please note:

The ‘Installation of a new meter’ fixed charge will be included on your first bill.

  • Temporary supply connection fee: $901.00 
    The charge to provide a single or three phase temporary connection to your premise while building works are carried out. 
  • Permanent power supply fee: $901.00 
    The charge to install and connect a single or three phase meter. Also charged when upgrading from a single to three phase meter.

If you are an existing customer, you will need your account number handy so that we can link your accounts in our system.

You will be provided with a Customer Reference Number (CRN). Please share the CRN with your builder and/or electrical contractor, as it needs to be quoted on future correspondence. 

  • Installation of a new meter form (ANPS)Download

 

Step five: Work is complete

Once the power supply is available at your property, your electrician or builder may need to carry out further work.

When your electrical contractor has completed their work, your contractor needs to submit the necessary electrical notices to us for approval (preliminary and completion notices). When these have been approved, your electricity will be connected (meter installed) and you will begin being invoiced for your power supply. 

Step one: Complete the Connection Application form  

  • The Connection Application form is used to connect an underground power supply to your property where there is currently none available. 
  • Submit the completed form online, or to your local Horizon Power office.
  • Do you also require a CT meter? Complete this form as well.
  • Connection application formDownload
  • Application for CT metering works formDownload

 

Step two: Pay the Design Fee

A design fee of $6,195.00 is payable for projects involving:

  • the supply of electricity to a connection with a total maximum load of between 31 kVA and 1000 kVA or 10% of the relevant systems peak load; or
  • CT metering that will result in an increase in the load capacity at the relevant site.

Step three: Accept the formal quote

Once you have received the formal quote and you want to proceed, simply sign the Quote Acceptance form and return it to us.

We will issue an invoice for the work which will need to be paid before any scheduling or construction can begin.

Please note: it can take up to 12 weeks for work to be completed from receipt of payment. 

Step four: Open an account with us and ask for a customer reference number

You can request a customer reference number (CRN) by phoning 1800 267 926 or you can request to install a new temporary or permanent meter using the form below. 

Please note:

The ‘Installation of a new meter’ fixed charge will be included on your first bill.

  • Temporary supply connection fee: $901.00 
    The charge to provide a single or three phase temporary connection to your premise while building works are carried out. 
  • Permanent power supply fee: $901.00 
    The charge to install and connect a single or three phase meter. Also charged when upgrading from a single to three phase meter.

If you are an existing customer, you will need your account number handy so that we can link your accounts in our system.

You will be provided with a Customer Reference Number (CRN). Please share the CRN with your builder and/or electrical contractor, as it needs to be quoted on future correspondence. 

  • Installation of a new meter form (ANPS)Download

 

Step five: Work is complete

Once the power supply is available at your property, your electrician or builder may need to carry out further work.

When your electrical contractor has completed their work, your contractor needs to submit the necessary electrical notices to us for approval (preliminary and completion notices). When these have been approved, your electricity will be connected (meter installed) and you will begin being invoiced for your power supply. 

Step one: Open an account with us and ask for a customer reference number

You can request a customer reference number (CRN) by phoning 1800 267 926 or you can request to install a new temporary or permanent meter using the form below.  

Please note:

The ‘Installation of a new meter’ fixed charge will be included on your first bill.

  • Temporary supply connection fee: $901.00 
    The charge to provide a single or three phase temporary connection to your premise while building works are carried out. 
  • Permanent power supply fee: $901.00 
    The charge to install and connect a single or three phase meter. Also charged when upgrading from a single to three phase meter.

If you are an existing customer, you will need your account number handy so that we can link your accounts in our system.

You will be provided with a Customer Reference Number (CRN). Please share the CRN with your builder and/or electrical contractor, as it needs to be quoted on future correspondence. 

  • Installation of a new meter form (ANPS)Download

 

Step two: Meter installed

When your electrical contractor has completed their work, your contractor needs to submit the necessary electrical notices to us for approval (preliminary and completion notices). When these have been approved, your electricity will be connected (meter installed) and you will begin being invoiced for your power supply. 

You can request to install a new temporary or permanent meter using the form below. 

Please note:

The ‘Installation of a new meter’ fixed charge will be included on your first bill.

  • Temporary supply connection fee: $901.00 
    The charge to provide a single or three phase temporary connection to your premise while building works are carried out. 
  • Permanent power supply fee: $901.00 
    The charge to install and connect a single or three phase meter. Also charged when upgrading from a single to three phase meter.

If you are an existing customer, you will need your account number handy so that we can link your accounts in our system.

You will be provided with a Customer Reference Number (CRN). Please share the CRN with your builder and/or electrical contractor, as it needs to be quoted on future correspondence. 

  • Installation of a new meter form (ANPS)Download

You can request to relocate one of our assets using the form below. If you need to relocate distribution equipment such as transformers, pillars and overhead lines, please complete this application form and we will provide a quote for the work required. Relocation is subject to a suitable alternative location and will be chargeable to the applicant.

  • Request for relocation of Horizon Power assets formDownload

Can't find what you're looking for?

Browse our list of forms, fees and charges.